By accelerate here, we mean complete the works before the agreed contractual date for completion of them, ie finish early. A Contractor has no obligation to accelerate, absent contrary provision in the contract, because its contractual duty is to complete the works by the completion date. Therefore it requires a new agreement (to accelerate) between […]

Before you gain access to our free CPD registered video Knowledge Hub, you need to create an account by providing us with your email address and password.  This will enable you to track your progress through the courses.  We will only use your email address to send you our newsletter and other valuable free content, sign up now!